Work is actually being done on the Islanders new home in Brooklyn..........
Atlantic Yards Arena and
Redevelopment Project
ATLANTIC YARDS CONSTRUCTION UPDATE
Weeks beginning October 8, 2007 and October 15, 2007
In an effort to keep the Atlantic Yards Community aware of upcoming
construction activities, ESD and Forest City Ratner are providing the
following outline of anticipated upcoming construction activities.
Please note: the scope and nature of activities are subject to change based
upon field conditions.
Long Island Rail Road/Vanderbilt Yard Work
Drilling piles at Southeast Gas Station (block 1121, lot 47).
Test pile for Temporary Train Trestle foundation piles is complete;
additional testing to continue to confirm structural failure.
Preparing to mobilize to East Portal to drill foundation piles by creating
earth ramps for drilling.
Preparing to mobilize to drill foundation piles for cable bridge (adjacent
to 6th Avenue Bridge).
Preparing to begin drilling trestle foundation piles.
Continue soil excavation and removal in block 1121 west to east.
Continue construction and debris removal.
Abatement and Demolition Work
All work described below will comply with the additional oversight and
protocols by the Department of Buildings (DOB) that were established on
April 30th.
Roof abatement at 800 Pacific Street (block 1129, lot 25) has been
completed. Clean-up will be underway within this two-week period.
Demolition at 546 Vanderbilt Avenue (block 1129, lot 54) is anticipated to
be underway for the next two-three months.
Demolition is anticipated to be underway at 814 Pacific Street (block 1129,
lot 45), 818 Pacific Street (block 1129, lot 46) and 542 Vanderbilt Avenue
(block 1129, lot 50) within this two-week period. Abatement will be
completed at 538 Vanderbilt Avenue (block 1129, lot 46) after a parapet is
removed, per the instructions of the BEST Squad.
Demolition is anticipated to be underway at 465 Dean Street (block 1127/lot
54) within this two-week period. >> Stay informed about: Construction update - Barclay Center - Isles new arena..... |
|
| Back to top |
|
 |  |
External

Since: Sep 05, 2006 Posts: 71
|
(Msg. 2) Posted: Thu Oct 18, 2007 11:00 pm
Post subject: Re: Construction update - Barclay Center - Isles new arena..... [Login to view extended thread Info.] Archived from groups: per prev. post (more info?)
|
|
|
On Thu, 18 Oct 2007 20:55:05 -0400, "Firebird" <firebird.TakeThisOut@nyc.rr.com>
wrote:
>Work is actually being done on the Islanders new home in Brooklyn..........
>
>Atlantic Yards Arena and
>Redevelopment Project
>
>ATLANTIC YARDS CONSTRUCTION UPDATE
>Weeks beginning October 8, 2007 and October 15, 2007
>
>In an effort to keep the Atlantic Yards Community aware of upcoming
>construction activities, ESD and Forest City Ratner are providing the
>following outline of anticipated upcoming construction activities.
>
>Please note: the scope and nature of activities are subject to change based
>upon field conditions.
>
>
>Long Island Rail Road/Vanderbilt Yard Work
>
>Drilling piles at Southeast Gas Station (block 1121, lot 47).
>
>Test pile for Temporary Train Trestle foundation piles is complete;
>additional testing to continue to confirm structural failure.
>
>Preparing to mobilize to East Portal to drill foundation piles by creating
>earth ramps for drilling.
>
>Preparing to mobilize to drill foundation piles for cable bridge (adjacent
>to 6th Avenue Bridge).
>
>Preparing to begin drilling trestle foundation piles.
>
>Continue soil excavation and removal in block 1121 west to east.
>
>Continue construction and debris removal.
>
>
>Abatement and Demolition Work
>
>All work described below will comply with the additional oversight and
>protocols by the Department of Buildings (DOB) that were established on
>April 30th.
>
>Roof abatement at 800 Pacific Street (block 1129, lot 25) has been
>completed. Clean-up will be underway within this two-week period.
>
>Demolition at 546 Vanderbilt Avenue (block 1129, lot 54) is anticipated to
>be underway for the next two-three months.
>
>Demolition is anticipated to be underway at 814 Pacific Street (block 1129,
>lot 45), 818 Pacific Street (block 1129, lot 46) and 542 Vanderbilt Avenue
>(block 1129, lot 50) within this two-week period. Abatement will be
>completed at 538 Vanderbilt Avenue (block 1129, lot 46) after a parapet is
>removed, per the instructions of the BEST Squad.
>
>Demolition is anticipated to be underway at 465 Dean Street (block 1127/lot
>54) within this two-week period.
>
I still say the Islanders will stay put.
Wang, and his partner bought the Marriott.
Reconstruction will be on the Island
Peace,
You have to be crazy to live in this world
Otherwise, you Will go insane :-]
WhereEaglesFly >> Stay informed about: Construction update - Barclay Center - Isles new arena..... |
|
| Back to top |
|
 |  |
External

Since: Jun 17, 2007 Posts: 261
|
(Msg. 3) Posted: Fri Oct 19, 2007 5:45 am
Post subject: Re: Construction update - Barclay Center - Isles new arena..... [Login to view extended thread Info.] Archived from groups: per prev. post (more info?)
|
|
|
Firebird wrote:
> Work is actually being done on the Islanders new home in Brooklyn..........
>
> Atlantic Yards Arena and
> Redevelopment Project
>
> ATLANTIC YARDS CONSTRUCTION UPDATE
> Weeks beginning October 8, 2007 and October 15, 2007
>
> In an effort to keep the Atlantic Yards Community aware of upcoming
> construction activities, ESD and Forest City Ratner are providing the
> following outline of anticipated upcoming construction activities.
>
> Please note: the scope and nature of activities are subject to change
> based upon field conditions.
I have to say, I thought it was hilarious that they tried to pull out
the "terrorism threat" card to slow down construction last week. >> Stay informed about: Construction update - Barclay Center - Isles new arena..... |
|
| Back to top |
|
 |  |
External

Since: Jan 02, 2007 Posts: 39
|
(Msg. 4) Posted: Fri Oct 19, 2007 6:49 am
Post subject: Re: Construction update - Barclay Center - Isles new arena..... [Login to view extended thread Info.] Archived from groups: per prev. post (more info?)
|
|
|
I did not know they bought the Marriott. But the Islander plan is to
refurbish the Coliseum. My thinking is....
Bruce Ratner is going to simply buy the Islanders and keep the offices on
the Island but they play in Brooklyn.
My thought all along has been Ratner is putting up this new palace....do you
think they plan for it to be dark 42 nights a year when they could house a
hockey team...I can't believe they would only house the Nets.
"WhereEaglesFly" <FUBAR.RemoveThis@Home.com> wrote in message
news:fp1gh396nm3oqg6looogm51lpq22ek7oic@4ax.com...
> On Thu, 18 Oct 2007 20:55:05 -0400, "Firebird" <firebird.RemoveThis@nyc.rr.com>
> wrote:
>
>>Work is actually being done on the Islanders new home in
>>Brooklyn..........
>>
>>Atlantic Yards Arena and
>>Redevelopment Project
>>
>>ATLANTIC YARDS CONSTRUCTION UPDATE
>>Weeks beginning October 8, 2007 and October 15, 2007
>>
>>In an effort to keep the Atlantic Yards Community aware of upcoming
>>construction activities, ESD and Forest City Ratner are providing the
>>following outline of anticipated upcoming construction activities.
>>
>>Please note: the scope and nature of activities are subject to change
>>based
>>upon field conditions.
>>
>>
>>Long Island Rail Road/Vanderbilt Yard Work
>>
>>Drilling piles at Southeast Gas Station (block 1121, lot 47).
>>
>>Test pile for Temporary Train Trestle foundation piles is complete;
>>additional testing to continue to confirm structural failure.
>>
>>Preparing to mobilize to East Portal to drill foundation piles by creating
>>earth ramps for drilling.
>>
>>Preparing to mobilize to drill foundation piles for cable bridge (adjacent
>>to 6th Avenue Bridge).
>>
>>Preparing to begin drilling trestle foundation piles.
>>
>>Continue soil excavation and removal in block 1121 west to east.
>>
>>Continue construction and debris removal.
>>
>>
>>Abatement and Demolition Work
>>
>>All work described below will comply with the additional oversight and
>>protocols by the Department of Buildings (DOB) that were established on
>>April 30th.
>>
>>Roof abatement at 800 Pacific Street (block 1129, lot 25) has been
>>completed. Clean-up will be underway within this two-week period.
>>
>>Demolition at 546 Vanderbilt Avenue (block 1129, lot 54) is anticipated to
>>be underway for the next two-three months.
>>
>>Demolition is anticipated to be underway at 814 Pacific Street (block
>>1129,
>>lot 45), 818 Pacific Street (block 1129, lot 46) and 542 Vanderbilt Avenue
>>(block 1129, lot 50) within this two-week period. Abatement will be
>>completed at 538 Vanderbilt Avenue (block 1129, lot 46) after a parapet is
>>removed, per the instructions of the BEST Squad.
>>
>>Demolition is anticipated to be underway at 465 Dean Street (block
>>1127/lot
>>54) within this two-week period.
>>
> I still say the Islanders will stay put.
> Wang, and his partner bought the Marriott.
> Reconstruction will be on the Island
> Peace,
> You have to be crazy to live in this world
> Otherwise, you Will go insane :-]
>
> WhereEaglesFly
> >> Stay informed about: Construction update - Barclay Center - Isles new arena..... |
|
| Back to top |
|
 |  |
External

Since: Sep 05, 2006 Posts: 71
|
(Msg. 5) Posted: Fri Oct 19, 2007 4:41 pm
Post subject: Re: Construction update - Barclay Center - Isles new arena..... [Login to view extended thread Info.] Archived from groups: per prev. post (more info?)
|
|
|
On Fri, 19 Oct 2007 06:49:42 -0400, "Firebird" <firebird DeleteThis @nyc.rr.com>
wrote:
>I did not know they bought the Marriott. But the Islander plan is to
>refurbish the Coliseum. My thinking is....
>Bruce Ratner is going to simply buy the Islanders and keep the offices on
>the Island but they play in Brooklyn.
>
>My thought all along has been Ratner is putting up this new palace....do you
>think they plan for it to be dark 42 nights a year when they could house a
>hockey team...I can't believe they would only house the Nets.
>
Another arena football team, Lacrosse team...
Anything But the Islanders
Peace,
You have to be crazy to live in this world
Otherwise, you Will go insane :-]
WhereEaglesFly >> Stay informed about: Construction update - Barclay Center - Isles new arena..... |
|
| Back to top |
|
 |  |
External

Since: Sep 05, 2006 Posts: 71
|
(Msg. 6) Posted: Fri Oct 19, 2007 4:41 pm
Post subject: Re: Construction update - Barclay Center - Isles new arena..... [Login to view extended thread Info.] Archived from groups: per prev. post (more info?)
|
|
|
On Fri, 19 Oct 2007 05:45:53 -0400, Cynicor
<j...tru.p..in RemoveThis @sp.eake.a.sy.net> wrote:
>I have to say, I thought it was hilarious that they tried to pull out
>the "terrorism threat" card to slow down construction last week.
You are one of my true friends in this group.
I pray, the Islanders stay on the Island.
My friends kid is finally playing on Ice, But having problems
stopping.
He scored 3 goals in his first game.
He is Jake Muno
Peace,
You have to be crazy to live in this world
Otherwise, you Will go insane :-]
WhereEaglesFly >> Stay informed about: Construction update - Barclay Center - Isles new arena..... |
|
| Back to top |
|
 |  |
External

Since: Jan 02, 2007 Posts: 39
|
(Msg. 7) Posted: Fri Oct 19, 2007 7:28 pm
Post subject: Re: Construction update - Barclay Center - Isles new arena..... [Login to view extended thread Info.] Archived from groups: per prev. post (more info?)
|
|
|
Brooklyn is on the Island!
"WhereEaglesFly" <FUBAR DeleteThis @Home.com> wrote in message
news:5s2ih3pep0nc8n498flcgdp2mo42d8d3k2@4ax.com...
> On Fri, 19 Oct 2007 05:45:53 -0400, Cynicor
> <j...tru.p..in DeleteThis @sp.eake.a.sy.net> wrote:
>
>
>>I have to say, I thought it was hilarious that they tried to pull out
>>the "terrorism threat" card to slow down construction last week.
>
> You are one of my true friends in this group.
> I pray, the Islanders stay on the Island.
>
> My friends kid is finally playing on Ice, But having problems
> stopping.
> He scored 3 goals in his first game.
> He is Jake Muno
>
> Peace,
> You have to be crazy to live in this world
> Otherwise, you Will go insane :-]
>
> WhereEaglesFly
> >> Stay informed about: Construction update - Barclay Center - Isles new arena..... |
|
| Back to top |
|
 |  |
External

Since: Sep 05, 2006 Posts: 71
|
(Msg. 8) Posted: Sat Oct 20, 2007 5:41 pm
Post subject: Re: Construction update - Barclay Center - Isles new arena..... [Login to view extended thread Info.] Archived from groups: per prev. post (more info?)
|
|
|
|
|
| Back to top |
|
 |  |
External

Since: Jan 02, 2007 Posts: 39
|
(Msg. 9) Posted: Sat Oct 20, 2007 10:07 pm
Post subject: Re: Construction update - Barclay Center - Isles new arena..... [Login to view extended thread Info.] Archived from groups: per prev. post (more info?)
|
|
|
Its clearly on Long Island....I know you are in Northern Connecticut....but
trust me Brooklyn besides being on Long Island always has been the capital
of the world....Then we can call the Islanders...the ISLANDIZ!!!!!
"WhereEaglesFly" <FUBAR.TakeThisOut@Home.com> wrote in message
news:9ftkh3hckprd454rmllutvd6mfknqquduo@4ax.com...
> On Fri, 19 Oct 2007 19:28:27 -0400, "Firebird" <firebird.TakeThisOut@nyc.rr.com>
> wrote:
>
>>Brooklyn is on the Island!
>
> BUT IS CLEARLY NOT ON LONG ISLAND
> othrwise, the maps would state it
> Peace,
> You have to be crazy to live in this world
> Otherwise, you Will go insane :-]
>
> WhereEaglesFly
> >> Stay informed about: Construction update - Barclay Center - Isles new arena..... |
|
| Back to top |
|
 |  |
|
You can post new topics in this forum You can reply to topics in this forum You can edit your posts in this forum You can delete your posts in this forum You can vote in polls in this forum
|
|
|
|
 |
|
|